References

Buildings in which the system is running.

Properties in Hesse and Bavaria: a sports facility, a town hall, schools, a parish and office buildings. The building types differ, the technology stays the same.

Buildings

Starting point, implementation and scope per building

AI-generated image of the TSV Bicken sports clubhouse

TSV Bicken sports clubhouse

Bicken, Lahn-Dill district
Sports clubhouse with changing rooms, built in the 1960s, around 300 m² of heated floor area

Control · Analysis · Monitoring

Starting point

The heating ran on a fixed programme, regardless of whether there was training. Consumption was around 270 kWh per square metre per year.

Implementation

Room-by-room control with weekly schedules, plus indoor climate sensors and leak detection.

In the project

€1,700savings per year
1.6 yearsto payback
36field devices (sensors & valve actuators), 15 of them valve actuators
2 weeksfrom site survey to operation
Mittenaar Town Hall

Mittenaar Town Hall

Mittenaar, Lahn-Dill district
Existing administrative building

Control

Starting point

Administrative operation with fixed opening hours and unevenly used rooms. Consumption was only known as an annual figure.

Implementation

Room-by-room control based on opening hours, analysis per room and limit value monitoring.

In the project

39field devices
2gateways for the entire building

No verified result figure is available for this building yet.

Johanneum Gymnasium (grammar school), Herborn
Lahn-Dill district

Johanneum Gymnasium

Herborn, Lahn-Dill district
Container classrooms with electric radiators

Control

Starting point

Poorly insulated containers. The radiators ran all night so that the rooms were warm when lessons began. The electricity bill was correspondingly high.

Implementation

Each radiator was fitted with a switching actuator with a stored heating schedule. Heating starts before lessons begin, and the power supply switches off after lessons end.

In the project

12switching actuators
1gateway
¾ dayon-site installation

Installation by Müller Schaltanlagen.

“The collaboration during on-site implementation was very good. The aim was to set up easily programmable control of the heating times for school containers with electric radiator heating, independent of intervention on site. Once the order was placed, all components were installed quickly and smoothly.”
Ingo DorstenHead of Energy Management, Lahn-Dill district
Ambachtalschule in Herborn-Burg

Photo: Uwe Seibert, CC BY-SA 2.0, cropped

Ambachtalschule

Herborn-Burg, Lahn-Dill district
Existing school building

Analysis · Monitoring

Starting point

Staff read the electricity meter by hand and then entered the values into a digital list. In addition, several doors had to be checked by hand regularly to make sure they were closed.

Implementation

The electricity meter is now read automatically and the values go straight into the platform. Door contacts monitor the doors and report when one is open.

In the project

4field devices
1gateway
documentedrange test before the quotation
AI-generated illustration of a school

AI-generated illustration

Pestalozzi-Schule

Herborn-Schönbach, Lahn-Dill district
Existing school building

Analysis · Monitoring

Starting point

Staff read the electricity meter by hand and then entered the values into a digital list. The temperature in the boiler room had to be checked on site every evening.

Implementation

The electricity meter is now read automatically and the values go straight into the platform. A sensor monitors the temperature in the boiler room and reports deviations by email.

In the project

2field devices
1outdoor gateway
documentedrange test before the quotation
Primary school in Eschenburg-Wissenbach

Photo: Otto Domes, CC BY-SA 4.0, cropped

Wissenbach Primary School

Wissenbach, Lahn-Dill district
Existing school building

Control · Monitoring

Starting point

School operation with holidays, off-peak hours and changing room use. Heating times could not be controlled per room.

Implementation

Control based on timetable and holiday schedule, indoor climate sensors for temperature, humidity and CO₂, and automatic reading of the electricity, gas and water meters.

In the project

40field devices
1gateway
documentedrange test before the quotation
Volanteq, Alter Hof Munich

Volanteq

Alter Hof, Munich
Office building, rented space

Analysis · Monitoring

Starting point

The tenant had reduced the rent by 20% during the winter months and complained about the air quality. There was no data basis for checking the complaint.

Implementation

Indoor climate measurement in the offices with history and current values. A limit value rule reports every exceedance.

Result

Since the measurements began, the air quality can be documented, and the rent has no longer been reduced because of the indoor air.

In the project

32field devices
3gateways
Self-installationinstallation by the building operator
½ dayinstallation per area
Church building with half-timbered chapel in the foreground

Catholic parish of Herborn

Herborn, Lahn-Dill district
Rectory and administrative building, poorly insulated

Control · Analysis

Starting point

In the winter months, the radiators often ran all night so that the rooms were warm when work began. The project was triggered by the heating cost statement.

Implementation

All radiators were fitted with valve actuators and a heating schedule: setback during closing times, timely heat-up before work begins.

In the project

42valve actuators
1gateway
½ dayon-site installation

Does one of these buildings match your property?

An initial consultation takes thirty minutes. Afterwards you know which applications fit, to what extent and how much of it federal funding covers.

FAQ

Frequently asked questions about this page

In which buildings is Sensise in use?

In properties in Hesse and Bavaria: a sports clubhouse, Mittenaar Town Hall, three primary schools, a grammar school, a parish and an office building in Munich. The building types differ, the technology stays the same.

How much does room-by-room heating control save in practice?

At the TSV Bicken sports clubhouse, built in the 1960s with around 300 m² of heated floor area, consumption was previously around 270 kWh per square metre per year. With room-by-room control and weekly schedules, the clubhouse saves €1,700 per year, and the system paid for itself after 1.6 years.

How long does on-site installation take?

Usually half a day to a full day: 42 valve actuators at the Catholic parish of Herborn were installed in half a day, 12 switching actuators at the Johanneum Gymnasium in three quarters of a day. At the TSV Bicken sports clubhouse, two weeks passed from the site survey to full operation.

How many gateways does a building need?

Usually one. At Wissenbach Primary School, one gateway receives 40 field devices, at the Catholic parish of Herborn 42 valve actuators. Mittenaar Town Hall manages with two gateways, the rented space in Munich with three. The range test before the quotation shows the exact number.

Can electric heating also be controlled?

Yes, via switching actuators on a schedule. At the Johanneum Gymnasium in Herborn, the radiators in container classrooms ran all night. Today, a switching actuator sits in front of each radiator: heating starts before lessons begin, and the power supply is off after lessons end.

Can indoor air measurements help with rent reductions?

Yes. A tenant in a Munich office building had reduced the rent by 20% in winter and complained about the air quality. Since the indoor climate measurement with a limit value rule was introduced, the air quality can be documented, and the rent has no longer been reduced because of the indoor air.

Can we speak to a reference customer?

In some cases, yes, after consulting the building operator. Ask about it in the initial consultation and we will find out who is available.